Puerto Rico energy chief orders LUMA to submit corrective plan over unspent $1B

The order requires the utility to produce the document within 10 days, with specified operational and financial reporting requirements.

Global Desk Correspondent
References:
Share on X
Stands on 19 placed sources from 2 publishers.
Puerto Rico Energy Czar Josue Colon has ordered LUMA Energy to prepare a corrective action plan within 10 days over roughly $1 billion in unspent funds from the 2025-2026 fiscal year.[1] As part of the required response, LUMA must provide detailed information on federal project statuses, billing data, and customer collections.[2] The directive follows a $1 billion shortfall between the funds allocated to the operator and what it actually spent that fiscal year.[3] Colon, who is also executive director of the Public-Private Partnerships Authority (P3A), put the demand in writing in a formal letter to LUMA dated November 10, 2026.[4] The letter requires a preliminary budget reconciliation within five business days and a full documented response within ten, and puts the unexecuted figure at approximately $1 billion in FY2026 budgeted expenditures.[5][6][7] The letter rejects the operator's explanation that funding disputes justify the shortfall. Between fiscal years 2022 and 2026, PREPA transferred approximately $4.92 billion to LUMA against approved budgets of approximately $4.08 billion - about $842.5 million more than budgeted.[8][9][10] P3A's position is that LUMA's capital-expenditure shortfalls are not justified by funding disputes or government decisions.[11] The letter is bluntest on federal reconstruction money. On the final consolidated FAASt project list sent to FEMA, 289 LUMA-managed projects were marked inactive: 65 were withdrawn by FEMA for insufficient progress, and 224 were affected by funding limits and development gaps, with an estimated combined cost of $5.5 billion.[12][13][14][15] The letter also flags $653.3 million in unreconciled federal advance funds still held by LUMA as of November 4, 2026.[16] The stakes show up in the grid's own numbers: Puerto Rico's SAIDI - the average outage duration per customer - worsened from 1,448 minutes in 2024 to 1,579 in 2025 and 1,705 in 2026.[17] The execution figures that triggered the letter were first reported by El Nuevo Dia on November 7, 2026: LUMA executed about 68% of its non-federal capital budget and 42% of its federally funded capital spending that fiscal year.[18][19]
References19 sources · 2 publishers
What this stands on
  1. Josué Colón, Puerto Rico's Energy Chief, ordered LUMA Energy to prepare a corrective action plan within 10 days regarding $1 billion in unspent funds from the 2025-2026 fiscal year. · El Nuevo DíaPuerto Rico
  2. LUMA Energy must provide detailed information on federal project statuses, billing data, and customer collections as part of the corrective action plan. · El Nuevo DíaPuerto Rico
  3. The directive follows LUMA Energy's reported $1 billion shortfall between allocated and spent funds during the 2025-2026 fiscal year. · El Nuevo DíaPuerto Rico
  4. Josué A. Colón Ortiz is P3A Executive Director and Puerto Rico Energy Czar. · bloximages.newyork1.vip.townnews.com
  5. LUMA had approximately $1 billion unexecuted FY2026 budgeted expenditures. · bloximages.newyork1.vip.townnews.com
  6. P3A requires LUMA submit preliminary budget reconciliation within 5 business days of receipt. · bloximages.newyork1.vip.townnews.com
  7. P3A requires LUMA submit full documented response within 10 business days of receipt. · bloximages.newyork1.vip.townnews.com
  8. PREPA transferred approximately $4.92 billion to LUMA between FY2022 and FY2026. · bloximages.newyork1.vip.townnews.com
  9. Total approved LUMA budgets for FY2022 through FY2026 were approximately $4.08 billion. · bloximages.newyork1.vip.townnews.com
  10. Cumulative PREPA transfers exceeded LUMA budgets by $842.5 million over FY2022 to FY2026. · bloximages.newyork1.vip.townnews.com
  11. P3A rejects claims that LUMA capital expenditure shortfalls are justified by funding disputes or government decisions. · bloximages.newyork1.vip.townnews.com
  12. 289 LUMA-managed projects were marked inactive in the Consolidated FAASt Project List. · bloximages.newyork1.vip.townnews.com
  13. 65 inactive LUMA projects were withdrawn by FEMA for lack of progress. · bloximages.newyork1.vip.townnews.com
  14. 224 inactive LUMA projects were affected by funding limits and development gaps. · bloximages.newyork1.vip.townnews.com
  15. The 224 inactive LUMA projects had an estimated combined cost of $5.5 billion. · bloximages.newyork1.vip.townnews.com
  16. As of November 4, 2026 LUMA had $653.3 million in unreconciled federal advance funds. · bloximages.newyork1.vip.townnews.com
  17. Puerto Rico SAIDI was 1448 minutes in 2024, 1579 minutes in 2025, 1705 minutes in 2026. · bloximages.newyork1.vip.townnews.com
  18. El Nuevo Día published a related article on November 7, 2026. · bloximages.newyork1.vip.townnews.com
  19. The El Nuevo Día article reported LUMA executed 68% of non-federal capital budget and 42% of federal capital budget last fiscal year. · bloximages.newyork1.vip.townnews.com
1 of the 2 publishers publishes from Puerto Rico. We do not know which country the other one publishes from. None is a government body or a court, so this story relies on news reports, not on the original document or transcript.