Governor Jenniffer González Colón says Puerto Rico is negotiating with Crowley, Naturgy and Javelin for new natural gas supply, as fuel shortages and rising electricity costs squeeze the island's grid.[1]
She said the contracting process has advanced to the contract-drafting stage, with the companies available to bring fuel once final terms are set.[2]
The urgency comes from the supplier itself: New Fortress Energy has disclosed that management's plans do not resolve the substantial doubt about its ability to continue as a going concern.[3] The primary driver is FLNG 1 - the company's principal source of LNG supply - which went offline in October after a mechanical failure in the facility's gas turbine.[4][5][6] NFE expects the floating unit back in service during the fourth quarter, but says the timing of the repair is outside its control.[7][8] The outage has impaired deliveries under NFE's supply agreement with PREPA, and parts of the Puerto Rico government have called for the agreement to be terminated outright.[9][10]
Meanwhile the fallout has a daily price tag: contract breaches have been costing $1.2 million per day in diesel burned to keep generation running.[11] There is also a structural catch: the alternative suppliers have refused to contract directly with New Fortress, and are demanding payment guarantees from the Electric Power Authority before delivering fuel.[12][13]La gobernadora Jenniffer González Colón indicó que Puerto Rico mantiene negociaciones con Crowley, Naturgy y Javelin para un nuevo suministro de gas natural, en un contexto donde la escasez de combustible y el alza de las tarifas eléctricas afectan la red de la isla.[1]
Señaló que el proceso de contratación avanzó hasta la etapa de redacción de contratos, y que las empresas están en condiciones de suministrar el combustible una vez se acuerden los términos finales.[2]
La urgencia se origina en el proveedor actual: New Fortress Energy informó que los planes de su dirección no eliminan la duda sustancial sobre la capacidad de la empresa para continuar operando de forma estable.[3] El factor principal es la unidad FLNG 1, principal fuente de suministro de gas natural licuado de la compañía, , que dejó de funcionar en octubre tras una falla mecánica en la turbina de gas de la instalación.[4][5][6] NFE estima que la unidad flotante volverá a estar operativa durante el cuarto trimestre, pero advirtió que el plazo de la reparación no está bajo su control.[7][8] Esta interrupción ha afectado los envíos establecidos en el contrato de suministro de NFE con la PREPA, y sectores del gobierno de Puerto Rico han solicitado la terminación inmediata de dicho acuerdo.[9][10]
Mientras tanto, esta situación genera costos diarios: los incumplimientos contractuales han generado gastos de 1.2 millones de dólares por día por el uso de diésel para mantener operativas las plantas de generación.[11] Existe además una condición estructural: los proveedores alternos se han negado a contratar directamente con New Fortress, y exigen garantías de pago por parte de la Autoridad de Energía Eléctrica antes de entregar combustible.[12][13]
References13 sources · 4 publishers
What this stands on
Jenniffer González Colón, Puerto Rico's governor, stated the government is negotiating with Naturgy, Javelin, and Crowley for new natural gas suppliers due to shortages and rising electricity costs. · Periódico La Perla
Jenniffer González Colón stated the new natural gas supplier hiring process is at contract drafting stage. · elvocero.com
Management plans do not resolve substantial going concern doubt. · document
The FLNG 1 outage was announced in October 2026. · document
FLNG 1 is NFE's principal LNG supply source. · document
FLNG 1 is offline due to a gas turbine mechanical issue. · document
NFE expects FLNG 1 to return to service in the fourth quarter of 2026. · document
FLNG 1 repair timing is not within NFE control. · document
The FLNG 1 outage has harmed NFE's ability to make current LNG deliveries. · document
Some Puerto Rico government parties have called for terminating the PREPA agreement. · document
Diesel use costs 1.2 million dollars daily from contract breaches. · eyboricua.com
Consulted gas suppliers refuse direct contracts with New Fortress Energy. · eyboricua.com
Consulted gas suppliers require payment guarantees from AEE. · eyboricua.com
We do not know which country they publish from. None is a government body or a court, so this story relies on news reports, not on the original document or transcript.