Puerto Rico Energy Bureau opens review of NFE LNG supply contract

Regulators launched the formal case November 20, as PREPA pursues damages over missed LNG deliveries this fall.

Global Desk Correspondent
References:
Share on WhatsAppShare on X
Stands on 8 sources from 3 publishers.
The Puerto Rico Energy Bureau opened Case No. NEPR-MI-2026-0009 on November 20 to review the natural gas supply contract between PREPA and NFEnergía. [1][2] The proceeding examines the contract's take-or-pay costs. [3] The review extends a September 30 order directing a comprehensive audit of New Fortress Energy-related costs, with $17.6 million in charges linked to NFE supply failures deferred pending that audit. [4][5] Under the December 2025 contract, PREPA must purchase a minimum of 40 million MMBtu of LNG annually under take-or-pay provisions. [6] NFE did not deliver contracted LNG between September 16 and October 13, forcing PREPA into additional diesel generation at an estimated $32 million in extra fuel costs. [7] PREPA has since filed federal lawsuits seeking approximately $55 million in damages for alleged breaches of the agreement. [8] Key termsTake-or-pay - A contract structure in which the buyer commits to purchase a minimum quantity - here a base annual minimum of 40 million MMBtu - whether or not it receives the full volume. [6] MMBtu - The energy unit the PREPA-NFE contract uses to set its minimum annual LNG purchase quantity of 40 million. [6]
References8 sources · 3 publishers
What this stands on
  1. The Puerto Rico Energy Bureau opened Case No. NEPR-MI-2026-0009 on November 20 to review the NFE LNG supply contract. · San Juan Daily Star
  2. Puerto Rico Energy Bureau opened proceeding case NEPR-MI-2026-0009. · energia.pr.govUnited Statesofficial source
  3. This proceeding reviews NFEnergía LLC natural gas take-or-pay costs. · energia.pr.govUnited Statesofficial source
  4. NEPR ordered an audit of New Fortress Energy related costs. · metro.prPuerto Rico
  5. NEPR deferred $17.6 million in costs linked to New Fortress Energy supply failures. · metro.prPuerto Rico
  6. The December 2025 LNG contract requires PREPA to purchase a minimum 40 million MMBtu annually with take-or-pay provisions. · San Juan Daily Star
  7. NFE failed to deliver contracted LNG between September 16 and October 13, causing an estimated $32 million in extra diesel costs for PREPA. · San Juan Daily Star
  8. PREPA filed federal lawsuits in 2026 seeking approximately $55 million in damages for alleged NFE supply contract breaches. · San Juan Daily Star