Former Autoridad de Energía Eléctrica director Justo González stated on Friday that Puerto Rico electricity consumers may face an upcoming bill increase. [1][2] González warned that rates may rise by 1 to 2 cents per kilowatt hour. [2]
The regulator's final ruling will determine if extra costs are passed to electricity consumers. [3] New Fortress Energy has not supplied natural gas to Puerto Rico since October and cannot resume service until further notice due to problems at its Mexican plant. [4] Three former directors of Puerto Rico's Autoridad de Energía Eléctrica stated in NotiCentro interviews that the exclusive port contract with New Fortress Energy should be canceled. [5]
Justo González stated natural gas supply disruptions from New Fortress Energy have forced use of diesel generation, which costs three times more than natural gas. [6][7] Unavailable generation unit Aguirre 1 is also requiring use of higher cost backup generators, according to González. [8] The Negociado de Energía de Puerto Rico is evaluating whether New Fortress Energy must compensate for the extra generation costs to avoid consumer price impacts. [9][10]Key termsNew Fortress Energy - the company tied to Puerto Rico's exclusive port natural gas supply contract; it has not supplied natural gas to the island since October and cannot resume service until further notice due to problems at its Mexican plant.Diesel generation - running power plants on diesel fuel instead of natural gas; the island's electrical system resorted to it after the gas supply disruptions, and it costs three times more than natural gas.Kilowatt-hour (kWh) - the unit in which electricity rates are priced; the warned bill increase would add 1 to 2 cents per kWh.
References10 sources · 3 publishers
What this stands on
Former Autoridad de Energía Eléctrica director Justo González stated on Friday that Puerto Rico electricity consumers may face an upcoming bill increase. · Metro Puerto RicoPuerto Rico
Former AEE director Justo González warned that electricity rates may increase by 1 to 2 cents per kilowatt hour · WAPA.TV
The regulator's final ruling will determine if extra costs are passed to electricity consumers · esnoticiapr.comPuerto Rico
New Fortress Energy has not supplied natural gas to Puerto Rico since October and cannot resume service until further notice due to problems at its Mexican plant · WAPA.TV
Three former directors of Puerto Rico's Autoridad de Energía Eléctrica stated in NotiCentro interviews that the exclusive port contract with New Fortress Energy should be canceled · WAPA.TV
Justo González stated natural gas supply disruptions from New Fortress Energy have forced use of diesel generation, which costs three times more than natural gas. · Metro Puerto RicoPuerto Rico
Natural gas supply disruptions have forced Puerto Rico's electrical system to use alternative diesel fuel for generation units · esnoticiapr.comPuerto Rico
Justo González stated unavailable generation unit Aguirre 1 is also requiring use of higher cost backup generators. · Metro Puerto RicoPuerto Rico
Regulators are evaluating whether New Fortress Energy must compensate for extra costs to avoid consumer price impacts · WAPA.TV
Negociado de Energía de Puerto Rico is evaluating if New Fortress Energy will be required to compensate for the extra generation costs · esnoticiapr.comPuerto Rico
2 of the 3 publishers publish from Puerto Rico. We do not know which country the other one publishes from. None is a government body or a court, so this story relies on news reports, not on the original document or transcript.