GAO cites five factors behind Puerto Rico grid reconstruction delays

Project reviews, staff rotation, financing complexity, PREPA's finances and uncertainty over involved entities are slowing the work.

Grid and Infrastructure Reporter
References:
Updated
Share on WhatsAppShare on X
Stands on 6 sources from 3 publishers and 1 first-party instrument reading.
A Government Accountability Office investigation identifies five factors behind delays in Puerto Rico grid reconstruction: project review processes, staff rotation, project financing complexity, the financial situation of the Puerto Rico Electric Power Authority, and uncertainty regarding involved entities. [1]