A mechanical failure at NFEnergía's Altamira plant in Mexico cut off the natural gas feeding units 5 and 6 of the Central San Juan power station, the company said in a disclosure filed Nov 5.[1]
Those two units account for roughly 15% of all electricity consumed in Puerto Rico, a figure confirmed in both filings.[2] NFEnergía projected it will resume gas deliveries to the island during the fourth quarter of 2026.[3] That window is wide: the quarter runs through December, and the disclosure fixes no firmer date.[4]
The Puerto Rico Electric Power Authority has taken NFEnergía to court over the outage.[5] The filings name the dispute but not the amount sought or the claims made.
The cause sits offshore, at a plant in Mexico, yet the lost capacity lands squarely on the island's grid. The projected fix rests on NFEnergía's own timeline, not a measured one.[1]Una falla mecánica en la planta de Altamira de NFEnergía en México cortó el gas natural que alimenta las unidades 5 y 6 de la Central San Juan, dijo la empresa en una divulgación radicada el 5 de noviembre.[1]
Esas dos unidades representan aproximadamente el 15% de toda la electricidad que se consume en Puerto Rico, una cifra confirmada en ambas radicaciones.[2] NFEnergía proyectó que reanudará las entregas de gas a la isla durante el cuarto trimestre de 2026.[3] Esa ventana es amplia: el trimestre se extiende hasta diciembre, y la divulgación no fija una fecha más firme.[4]
La Autoridad de Energía Eléctrica de Puerto Rico llevó a NFEnergía a los tribunales por la interrupción.[5] Las radicaciones nombran la disputa, pero no el monto reclamado ni las alegaciones hechas.
La causa está en alta mar, en una planta en México, pero la capacidad perdida recae de lleno sobre la red de la isla. El arreglo proyectado descansa en el propio calendario de NFEnergía, no en uno medido.[1]
Proof5 sources · 2 publishers · signed
What this stands on
NFEnergía stated that a mechanical failure at its Altamira, Mexico plant interrupted natural gas supply to units 5 and 6 of Puerto Rico's Central San Juan power station. · Metro Puerto RicoPuerto Rico
The affected Central San Juan units 5 and 6 supply approximately 15% of total electricity consumed in Puerto Rico. · Metro Puerto RicoPuerto Rico
NFEnergía projected it will resume natural gas deliveries to Puerto Rico during the fourth quarter of 2026. · Metro Puerto RicoPuerto Rico
Central San Juan units 5 and 6 are responsible for approximately 15% of Puerto Rico's total electricity consumption. · Periódico La Perla
The Puerto Rico Electric Power Authority has initiated legal proceedings against NFEnergía regarding this supply outage. · Periódico La Perla