Energy Bureau resets interconnection rulemaking - proposed regulation due Dec 7 as the 2027 solar wave nears

Fourteen comment sets forced a schedule change; final adoption of the DER rule is undated even as Marahú's 200 MW of solar and 285 MW of batteries head for the 2027 grid.

Global Desk Correspondent
References:
Share on X
Stands on 12 placed sources from 2 publishers.
Solar projects to boost Puerto Rico grid
Solar projects to boost Puerto Rico grid AI illustrationhow this picture was made
The Puerto Rico Energy Bureau has proposed a new Distributed Energy Resources interconnection regulation - the rules that would govern how distributed energy resources connect to the island's grid. [1] On November 13 the Bureau modified the rulemaking schedule after fourteen sets of comments came in on the second draft it had released on October 16. [2][3][4] Under the revised calendar, a notice of proposed regulation is due December 7, 2026, with comments on it due January 6, 2027. [5][6] The Bureau must complete the regulatory mandate from Joint Resolution #5-2026 by January 7, 2027 - but final adoption of the regulation itself has no set date. [7][8] The timing matters because a buildout is already heading for the 2027 grid in an energy system where average rates run around 34 cents per kilowatt-hour. [9][10] Among the approved projects is AES Puerto Rico's Marahú Solar and Storage complex in Salinas and Guayama, which pairs roughly 200 MW of solar generation with 285 MW of battery storage. [11] Approved renewable projects are also advancing in Coamo, Ponce, Peñuelas, Caguas and Juana Díaz. [12] Key termsInterconnection regulation - the proposed rule governing how distributed energy resources connect to the grid; a notice of proposed regulation is due December 7, 2026, and final adoption has no set date. Joint Resolution #5-2026 - the resolution whose regulatory mandate the Energy Bureau must complete by January 7, 2027. Battery storage - the 285 MW planned alongside Marahú's roughly 200 MW of solar generation in Salinas and Guayama.
References12 sources · 3 publishers
What this stands on
  1. The Puerto Rico Energy Bureau proposes a new Distributed Energy Resource Interconnection Regulation to modernize grid connections, with implementation planned for early 2027. · Metro Puerto RicoPuerto Rico
  2. The Energy Bureau modified the prior rulemaking schedule on November 13 2026. · energia.pr.govUnited Statesofficial source
  3. The Energy Bureau received 14 comment sets on the Second Draft regulation. · energia.pr.govUnited Statesofficial source
  4. On October 16 2026, the Energy Bureau released the Second Draft interconnection regulation. · energia.pr.govUnited Statesofficial source
  5. The revised schedule sets December 7 2026 for proposed regulation notice issuance. · energia.pr.govUnited Statesofficial source
  6. The revised schedule sets January 6 2027 as the proposed regulation comment deadline. · energia.pr.govUnited Statesofficial source
  7. The revised schedule sets January 7 2027 for Joint Resolution #5-2026 mandate completion. · energia.pr.govUnited Statesofficial source
  8. The final regulation adoption date is to be determined. · energia.pr.govUnited Statesofficial source
  9. Puerto Rico average electricity rates are around 34 cents per kilowatt-hour. · metro.prPuerto Rico
  10. Puerto Rico expects more renewable energy projects in 2027. · metro.prPuerto Rico
  11. AES Puerto Rico's Marahú Solar and Storage project in Salinas and Guayama will add 200 MW solar capacity and 285 MW battery storage, integrating into the grid by 2027. · Metro Puerto RicoPuerto Rico
  12. AEE approved renewable projects advance in Coamo, Ponce, Peñuelas, Caguas, Juana Díaz. · metro.prPuerto Rico
They publish from Puerto Rico, United States. 1 is an official body, so this traces to the document itself.