Puerto Rico grid work skips permits under emergency order

Executive Order 2025-016, signed in April 2025, strips permitting obligations from five grid operators - and work is already moving under it.

Grid and Infrastructure Reporter
References:
Updated
Share on WhatsAppShare on X
Stands on 18 sources from 5 publishers.
A project on Puerto Rico's electric grid was carried out without permits under Executive Order 2025-016, the emergency measure Governor Jenniffer González signed to speed work on the electric system - and Negrón Díaz said the project did not require permits because the order covered it, esnoticiapr.com reports.[1] The exemption regime is no longer theoretical: it has now been used to move actual grid work past the permitting desk.