Puerto Rico to present potential Crowley gas tolling deal to federal judge as NFE restart date stays unset

Puerto Rico's power authority faces estimated additional daily costs while operating on backup diesel

Global Desk Correspondent
References:
Share on X
Stands on 14 placed sources from 4 publishers.
Governor Jenniffer González Colón said a potential liquefied natural gas tolling agreement with Crowley - the closest to signing among the alternate suppliers - will be presented to federal magistrate Héctor Ramos Vega at a court hearing.[1] The government's third-party procurement office has reached an agreement with an alternate LNG supplier, and the arrangement covers delivery by ship to the Puerto Nuevo terminal as well as ISO containers trucked directly to temporary generation units.[2][3] New Fortress Energy failed to meet its natural gas delivery obligations and stopped supplying the island in late October.[4][5] NFEnergía LLC responded that it is available to complete the agreement that would let an alternate supplier use its facilities to bring gas to the San Juan and Palo Seco power plants, and that it can meet with the parties immediately to formalize it.[6][7] The company said it notified the Federal Court on November 2 that its facilities were available for that purpose, and that it has negotiated in good faith while maintaining its position of complying with the current contract.[8][9] Talks with Naturgy and Javelin remain in the negotiation stage and could also produce agreements.[10] Even so, New Fortress Energy has not provided a date for restored LNG deliveries to the Puerto Rico Electric Power Authority.[11] The Public Private Partnership Authority has estimated $1.25 million in additional daily power costs while the grid runs on diesel.[12] Alternate suppliers would use the terminal under the tolling mechanism defined in the existing NFEnergía-PREPA contract.[13] NFEnergía has submitted operational procedures, technical requirements and draft agreement documents to the authority.[14]
References14 sources · 4 publishers
What this stands on
  1. The Government will report a possible natural gas supply agreement with Crowley to Federal Court. · elvocero.com
  2. Governor Jenniffer González Colón announced 3PPO reached an agreement with an alternate liquefied natural gas supplier. · metro.prPuerto Rico
  3. The potential Crowley agreement includes LNG supply by ship and truck. · elvocero.com
  4. New Fortress Energy failed to meet its natural gas delivery contract obligations. · elvocero.com
  5. New Fortress Energy stopped LNG supplies to Puerto Rico in late October. · elvocero.com
  6. NFEnergía LLC stated it is available to complete an agreement for an alternate natural gas supplier to use its facilities. · metro.prPuerto Rico
  7. NFEnergía can meet immediately with parties to formalize the agreement. · metro.prPuerto Rico
  8. NFEnergía notified the Federal Court its facilities were available on November 2. · metro.prPuerto Rico
  9. NFEnergía stated it negotiated in good faith and will comply with its current contract. · metro.prPuerto Rico
  10. Natural gas supply talks are ongoing with Naturgy and Javelin. · elvocero.com
  11. New Fortress Energy has not provided a date for restored LNG deliveries to Puerto Rico's Electric Power Authority · Periódico La Perla
  12. Puerto Rico's Public Private Partnership Authority estimated $1.25 million daily additional power costs while running on diesel · Periódico La Perla
  13. Third party natural gas supplier access uses a tolling mechanism defined in the existing contract between NFEnergía and the Puerto Rico Electric Power Authority. · WIPR
  14. NFEnergía has submitted operational procedures, technical requirements and draft agreement documents to the Puerto Rico Electric Power Authority. · WIPR