A Senate inquiry into IntegraPR - the ERP platform that took over the Puerto Rico government's finances in July - held a second hearing on November 12 with Deloitte Consulting LLP and ASG attending, after Deloitte skipped the first one on November 9.[1][2][3] The unresolved subject: thousands of contractors waiting to be paid under the new system.[4]The scale of the stall
Manually processing the stuck invoices - the workaround on the table - runs 45 to 90 minutes per transaction.[5] Since July, the platform has processed 80,692 invoices worth about $5.95 billion, while 2,373 school-transportation invoices worth $7.4 million remain unpaid.[6][7] Monthly financial closures have not been completed since the system launched.[8]The contract
Deloitte's implementation contract has been amended 14 times, its maximum value now $86.4 million,[9] with $67.6 million already paid.[10]The federal fallout
Sen. Carmelo Ríos Santiago said the ERP's problems postponed the scheduled exit of the federal monitor inside the Department of Education, at a cost of about $4 million.[11] On November 20, the Fiscal Oversight Board approved a three-month extension of federal oversight for the department, citing unresolved implementation failures with the ERP system, at a cost exceeding $3.9 million.[12][13]
One partial fix is moving: OGP approved a $9 million request for pending school-transporter payments.[14]Key termsERP (IntegraPR) - The enterprise resource planning platform meant to centralize the Puerto Rico government's financial processes - budgets, invoices, payments - in one electronic system, live since July 2026.Una investigación del Senado sobre IntegraPR, la plataforma ERP que asumió la administración de las finanzas del Gobierno de Puerto Rico en julio, celebró su segunda vista el 12 de noviembre con la presencia de Deloitte Consulting LLP y ASG, luego que Deloitte no asistiera a la primera del 9 de noviembre.[1][2][3] El tema pendiente: miles de contratistas que esperan cobrar a través del nuevo sistema.[4]La magnitud del retraso
El procesamiento manual de las facturas atascadas, la medida provisional que se evalúa, toma entre 45 y 90 minutos por transacción.[5] Desde julio, la plataforma ha procesado 80.692 facturas por un valor aproximado de $5.95 mil millones, mientras que 2.373 facturas de transporte escolar por $7.4 millones permanecen impagas.[6][7] No se han completado cierres financieros mensuales desde que se puso en operación el sistema.[8]El contrato
El contrato de implementación de Deloitte ha sido modificado 14 veces. Su valor máximo actual es de $86.4 millones,[9] de los cuales ya se han desembolsado $67.6 millones.[10]Consecuencias a nivel federal
El senador Carmelo Ríos Santiago indicó que los fallos del ERP retrasaron la salida programada del monitor federal asignado al Departamento de Educación, con un costo aproximado de $4 millones.[11] El 20 de noviembre, la Junta de Supervisión Fiscal aprobó una extensión de tres meses de la supervisión federal para el departamento, justificando la medida por fallos no resueltos en la implementación del sistema ERP, por un costo superior a $3.9 millones.[12][13]
Una solución parcial ya avanza: la OGP aprobó una solicitud de $9 millones para pagos pendientes a transportistas escolares.[14]Términos claveERP (IntegraPR), Plataforma de planificación de recursos empresariales diseñada para centralizar todos los procesos financieros del Gobierno de Puerto Rico, presupuestos, facturas, pagos, en un solo sistema electrónico, en operación desde julio de 2026.
References14 sources · 3 publishers
What this stands on
The Puerto Rico Senate held a public hearing on the IntegraPR ERP financial system on 2026-11-12. · senado.pr.govUnited Statesofficial source
Representatives from Deloitte Consulting LLP and ASG attended the hearing. · senado.pr.govUnited Statesofficial source
Deloitte did not attend the 9 November 2026 commission hearing. · senado.pr.govUnited Statesofficial source
The ERP system stops thousands of contractors from getting paid. · senado.pr.govUnited Statesofficial source
Manual invoice processing takes 45 to 90 minutes per transaction. · senado.pr.govUnited Statesofficial source
IntegraPR has processed 80692 invoices worth about 5.95 billion dollars since July 2026. · senado.pr.govUnited Statesofficial source
2373 school transportation invoices worth 7.4 million dollars remain unpaid. · senado.pr.govUnited Statesofficial source
Monthly financial closures have not been completed since IntegraPR launched in July 2026. · senado.pr.govUnited Statesofficial source
The Deloitte contract has been amended 14 times, maximum value now 86.4 million dollars. · senado.pr.govUnited Statesofficial source
67.6 million dollars have been paid to Deloitte under this contract. · senado.pr.govUnited Statesofficial source
Senator Carmelo Ríos stated ÍntegraPR delays postponed the federal education monitor exit, costing $4 million. · noticel.comPuerto Rico
The oversight extension was required due to unresolved implementation failures with the Puerto Rico government ERP administrative and financial system. · The Borinquen Post
The Puerto Rico Fiscal Oversight Board approved a 3-month extension of federal oversight for the Department of Education on November 20, at a total cost exceeding $3.9 million. · The Borinquen Post
OGP approved 9 million dollars for pending school transporter payments. · senado.pr.govUnited Statesofficial source
They publish from United States, Puerto Rico. We do not know which country the other one publishes from. 1 is an official body, so this traces to the document itself.