Energy Bureau approves $4,015,000 for Consent Decree outages at Costa Sur and Palo Seco, denies FY2028 request

The regulator funded only the two units facing 2027 compliance windows and told Genera to document its federal funding pursuit before ratepayers cover the rest.

Editor-in-Chief
References:
Share on X
Stands on 20 placed sources from 4 publishers.
The Puerto Rico Energy Bureau has approved an amendment to Genera PR's fiscal 2027 budget adding $4,015,000 to pay for federally mandated environmental outages at two power plants.[1] The work covers Costa Sur Unit 5 and Palo Seco Unit 4.[2] The Bureau allocated the $4,015,000 from the unallocated balance of the FY26 Reconciliation Amount.[3]