PREPA seeks $100M from New Fortress Energy over undelivered gas

The amended federal suit cites $32M in excess diesel costs during a 28-day gas outage from Sept. 16 to Oct. 13.

Grid and Infrastructure Reporter
Share on X
Stands on 4 placed sources from 2 publishers.
The Puerto Rico Electric Power Authority has filed an amended federal lawsuit seeking at least $100 million in damages from New Fortress Energy for undelivered gas and related costs, NotiCel reports. [1] The utility ran on diesel when the gas stopped. NotiCel reports PREPA incurred $32 million in excess diesel generation costs during a 28-day New Fortress Energy gas delivery outage between Sept. 16 and Oct. 13. [2] That is the hard number behind the claim: nearly a month of a plant burning the more expensive fuel because the contracted gas did not arrive. The contract fight has drawn fire at the Capitol. Metro Puerto Rico reports Denis Márquez Lebrón alleged New Fortress Energy has repeatedly failed to deliver contracted gas supplies, forcing PREPA to buy additional diesel. [3] He also stated the company never delivered the promised electricity bill savings, and that Puerto Rico now has the highest power rates in its history, Metro Puerto Rico reports. [4] The through-line is the gas. The diesel cost PREPA cites in court is the same undelivered supply Márquez Lebrón points to at the Capitol. The figure to hold is the $32 million the utility says it spent on diesel over those 28 days.
Proof4 sources · 2 publishers · signed
What this stands on
  1. The Puerto Rico Electric Power Authority filed an amended federal lawsuit on Monday seeking at least $100 million in damages from New Fortress Energy for undelivered gas and related costs. · NotiCel - La verdad como es - Noticias de Puerto Rico - NOTICEL -Puerto Rico
  2. The Puerto Rico Electric Power Authority incurred $32 million in excess diesel generation costs during the 28 day New Fortress Energy gas delivery outage between 16 September and 13 October. · NotiCel - La verdad como es - Noticias de Puerto Rico - NOTICEL -Puerto Rico
  3. Denis Márquez Lebrón alleged New Fortress Energy has repeatedly failed to deliver contracted gas supplies, forcing the Puerto Rico Electric Power Authority to purchase additional diesel. · Metro Puerto RicoPuerto Rico
  4. Denis Márquez Lebrón stated that New Fortress Energy never delivered promised electricity bill savings, and instead Puerto Rico now has the highest power rates in its history. · Metro Puerto RicoPuerto Rico
All of them publish from Puerto Rico. None is an official body: that part stands on reporting, not on the underlying document or transcript.