CNE: LUMA missed outage targets; Puerto Rico reports 2025 insurance growth

Reports published October 13 through 15 cover grid operator performance, insurance industry figures and economic strategy proposals.

Grid and Infrastructure Reporter
Share on X
Stands on 17 placed sources from 4 publishers.
Analysis from the Center for a New Economy found that after 15 months operating Puerto Rico’s power grid, LUMA Energy has exceeded budgets and failed to meet required performance metrics for outage duration and frequency.[1] CNE policy director Sergio M. Marxuach also wrote that separate proposals from the Pierluisi administration and the Financial Oversight and Management Board do not add up to a comprehensive economic strategy for the territory.[2] The analysis was published in the CNE Review.[3] This week also saw release of 2025 insurance industry data from Puerto Rico’s Office of the Insurance Commissioner. Total written premiums reached $24,021 million for the year, 9.1% growth over 2024.[4] [5] Law 130 of 2025, enacted that November, amended the territory’s insurance code with new compliance rules.[6] Commissioner Suzette Del Valle Lecároz called the insurance industry core economic and social infrastructure.[7] Separately, the Energy Bureau ordered LUMA on 14 October to complete technical studies within eight weeks to locate connection points for 800 megawatts of temporary generation; noncompliance can bring daily administrative fines.[8][9][10] Puerto Rico's peak power demand reached about 3,234 megawatts in August 2026.[11] The Bureau's review of LUMA's FY2025 performance is continuing, with quarterly reports filed through July 2025 and information requests due within ten business days.[12][13] On the insurance side, industry employment rose 24.9% from 2024 to 2025, with 386 insurance, reinsurance and health firms operating at end of 2025; premiums have grown roughly 36% over five years and now equal 18.6% of GDP.[14][15][16][17]
Proof17 sources · 5 publishers · signed
What this stands on
  1. After 15 months of operation, LUMA Energy has exceeded its budgets and failed to meet key performance metrics regarding the duration and frequency of power outages in Puerto Rico. · CNE - Centro Para Una Nueva Economía - Center for a New Economy
  2. Sergio M. Marxuach, director of Public Policy, stated that the Pierluisi Administration and the Financial Oversight and Management Board (FOMB) have proposed new economic incentives and structural reforms, but both efforts fall short of designing a comprehensive economic strategy. · CNE - Centro Para Una Nueva Economía - Center for a New Economy
  3. Sergio M. Marxuach, Policy Director of the CNE, published an analysis in the CNE Review regarding the PREPA-LUMA Operation and Maintenance Agreement in September 2022. · CNE - Centro Para Una Nueva Economía - Center for a New Economy
  4. Suzette Del Valle Lecároz reported total written insurance premiums in Puerto Rico reached approximately $24,021 million in 2025. · Metro Puerto RicoPuerto Rico
  5. Puerto Rico Office of the Insurance Commissioner 2025 annual report stated total industry written premiums reached $24 billion, 9.1% growth over 2024 · Metro Puerto RicoPuerto Rico
  6. Puerto Rico enacted Law 130 of 2025 in November 2025 amending the insurance code with new compliance requirements · Metro Puerto RicoPuerto Rico
  7. Puerto Rico Insurance Commissioner Suzette Del Valle Lecároz stated the insurance industry is core economic and social infrastructure for the territory. · Metro Puerto RicoPuerto Rico
  8. El Negociado de Energía of Puerto Rico ordered LUMA Energy to finish technical studies within eight weeks. · noticel.comPuerto Rico
  9. The studies will locate connection points for 800 megawatts of temporary power generation. · noticel.comPuerto Rico
  10. Order noncompliance may result in daily administrative fines and legal sanctions. · noticel.comPuerto Rico
  11. Puerto Rico peak power demand reached about 3234 megawatts in August 2026. · noticel.comPuerto Rico
  12. The Puerto Rico Energy Bureau reviewed LUMA FY2025 quarterly reports. · energia.pr.govUnited Statesofficial source
  13. LUMA must respond to listed information requests within 10 business days. · energia.pr.govUnited Statesofficial source
  14. Insurance industry employment rose 24.9% from 2024 to 2025. · metro.prPuerto Rico
  15. 386 insurance, reinsurance and health firms operated in Puerto Rico at end 2025. · metro.prPuerto Rico
  16. Insurance premiums grew approximately 36% over five years ending 2025. · metro.prPuerto Rico
  17. 2025 insurance premiums equalled 18.6% of Puerto Rico GDP. · metro.prPuerto Rico