The Federal Tribunal for the District of Puerto Rico granted a provisional injunction requested by the Autoridad de Energía Eléctrica ordering NFEnergía LLC to allow alternative natural gas suppliers access to its facilities. [1][2][4][5][8]
The court order prohibits New Fortress from blocking alternative gas supplier access or conditioning access on disputed invoice payments. [3][9] The Fiscal Oversight Board stated that ongoing breach of the natural gas supply agreement by New Fortress Energy threatens certified fiscal plans and Puerto Rico's economic recovery. [6] The Puerto Rico Fiscal Oversight Board filed an urgent federal court motion on Friday seeking to intervene as plaintiff in the AEE lawsuit against New Fortress Energy, NFEnergía and Atlantic Energy Holdings. [7]
New Fortress Energy is required within 24 hours to disclose natural gas quantities aboard the Amur River vessel and projected supply exhaustion timing. [10] The court ruled that interruption of natural gas supply would force diesel generator use, reducing efficiency and increasing grid failure risk constituting irreparable harm. [11] Judge Pedro A. Delgado Hernández ordered New Fortress to provide remaining gas inventory, depletion timeline and next shipment details within 24 hours. [12]El Tribunal Federal para el Distrito de Puerto Rico concedió un interdicto provisional solicitado por la Autoridad de Energía Eléctrica que ordena a NFEnergía LLC permitir a suplidores alternos de gas natural el acceso a sus instalaciones. [1][2][4][5][8]
La orden del tribunal prohíbe a New Fortress bloquear el acceso de suplidores alternos de gas o condicionar el acceso al pago de facturas en disputa. [3][9] La Junta de Supervisión Fiscal indicó que el continuo incumplimiento del acuerdo de suministro de gas natural por parte de New Fortress Energy amenaza los planes fiscales certificados y la recuperación económica de Puerto Rico. [6] La Junta de Supervisión Fiscal de Puerto Rico presentó una moción urgente ante el tribunal federal el viernes para intervenir como demandante en la demanda de la AEE contra New Fortress Energy, NFEnergía y Atlantic Energy Holdings. [7]
Se requiere a New Fortress Energy que, dentro de 24 horas, divulgue las cantidades de gas natural a bordo del buque Amur River y el momento proyectado en que se agotaría el suministro. [10] El tribunal dictaminó que la interrupción del suministro de gas natural obligaría al uso de generadores de diésel, reduciendo la eficiencia y aumentando el riesgo de fallo de la red, lo que constituye un daño irreparable. [11] El juez Pedro A. Delgado Hernández ordenó a New Fortress proveer el inventario de gas restante, el cronograma de agotamiento y los detalles del próximo cargamento dentro de 24 horas. [12]
Proof12 sources · 4 publishers
What this stands on
Puerto Rico Federal Tribunal issued an order on Friday requiring New Fortress Energy to allow alternate natural gas suppliers access to its facilities. · Telemundo Puerto RicoPuerto Rico
The Federal Tribunal for the District of Puerto Rico granted a provisional injunction requested by the Autoridad de Energía Eléctrica ordering NFEnergía LLC to allow alternative natural gas suppliers access to its facilities. · Metro Puerto RicoPuerto Rico
The court order prohibits New Fortress from blocking alternative gas supplier access or conditioning access on disputed invoice payments. · esnoticiapr.com
The Federal Court for the District of Puerto Rico granted on Friday a temporary injunction requested by the Puerto Rico Electric Power Authority against NFEnergía LLC. · esnoticiapr.com
On 2025-10-30, Puerto Rico Federal Judge Pedro A. Delgado Hernández issued a 14-day emergency order prohibiting NFEnergía from blocking third party natural gas deliveries for AEE · Periódico La Perla
The Fiscal Oversight Board stated that ongoing breach of the natural gas supply agreement by New Fortress Energy threatens certified fiscal plans and Puerto Rico's economic recovery. · Metro Puerto RicoPuerto Rico
The Puerto Rico Fiscal Oversight Board filed an urgent federal court motion on Friday seeking to intervene as plaintiff in the AEE lawsuit against New Fortress Energy, NFEnergía and Atlantic Energy Holdings. · Metro Puerto RicoPuerto Rico
Judge Pedro A. Delgado Hernández issued the order in response to a Puerto Rico government urgent request over gas supply failures. · Telemundo Puerto RicoPuerto Rico
New Fortress Energy is prohibited from blocking alternate gas deliveries or conditioning access on payment of disputed invoices. · Telemundo Puerto RicoPuerto Rico
New Fortress Energy is required within 24 hours to disclose natural gas quantities aboard the Amur River vessel and projected supply exhaustion timing. · Telemundo Puerto RicoPuerto Rico
The court ruled that interruption of natural gas supply would force diesel generator use, reducing efficiency and increasing grid failure risk constituting irreparable harm. · Metro Puerto RicoPuerto Rico
Judge Pedro A. Delgado Hernández ordered New Fortress to provide remaining gas inventory, depletion timeline and next shipment details within 24 hours. · esnoticiapr.com