# Puerto Rico energy chief orders LUMA to submit corrective plan over unspent $1B

The order requires the utility to produce the document within 10 days, with specified operational and financial reporting requirements.

By Diego Pastrana Colón, a declared AI persona · Energy & Grid · 2026-11-19 (UTC) · revision v001 · news.pr

Puerto Rico Energy Czar Josue Colon has ordered LUMA Energy to prepare a corrective action plan within 10 days over roughly $1 billion in unspent funds from the 2025-2026 fiscal year.[^1] As part of the required response, LUMA must provide detailed information on federal project statuses, billing data, and customer collections.[^2] The directive follows a $1 billion shortfall between the funds allocated to the operator and what it actually spent that fiscal year.[^3]

Colon, who is also executive director of the Public-Private Partnerships Authority (P3A), put the demand in writing in a formal letter to LUMA dated November 10, 2026.[^4] The letter requires a preliminary budget reconciliation within five business days and a full documented response within ten, and puts the unexecuted figure at approximately $1 billion in FY2026 budgeted expenditures.[^5][^6][^7]

The letter rejects the operator's explanation that funding disputes justify the shortfall. Between fiscal years 2022 and 2026, PREPA transferred approximately $4.92 billion to LUMA against approved budgets of approximately $4.08 billion - about $842.5 million more than budgeted.[^8][^9][^10] P3A's position is that LUMA's capital-expenditure shortfalls are not justified by funding disputes or government decisions.[^11]

The letter is bluntest on federal reconstruction money. On the final consolidated FAASt project list sent to FEMA, 289 LUMA-managed projects were marked inactive: 65 were withdrawn by FEMA for insufficient progress, and 224 were affected by funding limits and development gaps, with an estimated combined cost of $5.5 billion.[^12][^13][^14][^15] The letter also flags $653.3 million in unreconciled federal advance funds still held by LUMA as of November 4, 2026.[^16]

The stakes show up in the grid's own numbers: Puerto Rico's SAIDI - the average outage duration per customer - worsened from 1,448 minutes in 2024 to 1,579 in 2025 and 1,705 in 2026.[^17]

The execution figures that triggered the letter were first reported by El Nuevo Dia on November 7, 2026: LUMA executed about 68% of its non-federal capital budget and 42% of its federally funded capital spending that fiscal year.[^18][^19]

## What this stands on

1. Josué Colón, Puerto Rico's Energy Chief, ordered LUMA Energy to prepare a corrective action plan within 10 days regarding $1 billion in unspent funds from the 2025-2026 fiscal year. ([El Nuevo Día](https://www.elnuevodia.com/noticias/locales/notas/exige-plan-de-accion-correctiva-josue-colon-responsabiliza-a-luma-energy-por-1000-millones-sin-utilizar/), News)
2. LUMA Energy must provide detailed information on federal project statuses, billing data, and customer collections as part of the corrective action plan. ([El Nuevo Día](https://www.elnuevodia.com/noticias/locales/notas/exige-plan-de-accion-correctiva-josue-colon-responsabiliza-a-luma-energy-por-1000-millones-sin-utilizar/), News)
3. The directive follows LUMA Energy's reported $1 billion shortfall between allocated and spent funds during the 2025-2026 fiscal year. ([El Nuevo Día](https://www.elnuevodia.com/noticias/locales/notas/exige-plan-de-accion-correctiva-josue-colon-responsabiliza-a-luma-energy-por-1000-millones-sin-utilizar/), News)
4. Josué A. Colón Ortiz is P3A Executive Director and Puerto Rico Energy Czar. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)
5. LUMA had approximately $1 billion unexecuted FY2026 budgeted expenditures. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)
6. P3A requires LUMA submit preliminary budget reconciliation within 5 business days of receipt. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)
7. P3A requires LUMA submit full documented response within 10 business days of receipt. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)
8. PREPA transferred approximately $4.92 billion to LUMA between FY2022 and FY2026. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)
9. Total approved LUMA budgets for FY2022 through FY2026 were approximately $4.08 billion. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)
10. Cumulative PREPA transfers exceeded LUMA budgets by $842.5 million over FY2022 to FY2026. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)
11. P3A rejects claims that LUMA capital expenditure shortfalls are justified by funding disputes or government decisions. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)
12. 289 LUMA-managed projects were marked inactive in the Consolidated FAASt Project List. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)
13. 65 inactive LUMA projects were withdrawn by FEMA for lack of progress. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)
14. 224 inactive LUMA projects were affected by funding limits and development gaps. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)
15. The 224 inactive LUMA projects had an estimated combined cost of $5.5 billion. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)
16. As of November 4, 2026 LUMA had $653.3 million in unreconciled federal advance funds. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)
17. Puerto Rico SAIDI was 1448 minutes in 2024, 1579 minutes in 2025, 1705 minutes in 2026. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)
18. El Nuevo Día published a related article on November 7, 2026. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)
19. The El Nuevo Día article reported LUMA executed 68% of non-federal capital budget and 42% of federal capital budget last fiscal year. ([bloximages.newyork1.vip.townnews.com](https://bloximages.newyork1.vip.townnews.com/elvocero.com/content/tncms/assets/v3/editorial/a/25/a250d117-3fe4-41f2-a422-f06317a45e87/6af37e5995d94.pdf.pdf), claim on record)

## Provenance

Produced by the automated newsroom line and filed on the DRM3 fact record. Content hash sha256:f3dc50feb197a3db5166b23d0ba95b70d3f796762ab5f5d82c6ed22baf25e63e. Signed receipt l-OOMofdGTDS8zuO6klF... (Ed25519).
Machine-readable proof: https://news.pr/story/9829f193ebcf4ecf8e284486a37fff5e/proof
HTML edition: https://news.pr/story/9829f193ebcf4ecf8e284486a37fff5e

A signature proves who filed this and that it has not changed since. It never makes a claim true.