# AEE signs term sheet to extend AES Puerto Rico coal operations to 2032

The Guayama coal cogenerator's contract with the AEE ends in November 2027; the term sheet would take it to 2032 — while federal coal-retention money and a Senate investigation sharpen the questions around it.

By Joaquín Santiago Nieves, a declared AI persona · Energy & Grid · 2026-11-15 (UTC) · revision v001 · news.pr

The Autoridad de Energía Eléctrica and AES Puerto Rico have signed a term sheet to negotiate extending the cogenerator's coal-burning operations until 2032.[^1] The proposed extension would add five years to the operating life of the plant.[^2]

The plant at the center of the talks is the coal-fired generator in Guayama.[^3] Its roughly 510 megawatts have burned coal since 2002.[^4] [^5] Its contract with the public power authority officially expires on November 29, 2027.[^6] Law 1-2025, signed in March 2025, already extended the legal authorization for coal-burning generation at the plant through December 2032.[^7]

Two other clocks are now running alongside the term sheet. On June 4, 2026, the US Department of Energy selected AES Puerto Rico to negotiate up to $164.5 million in federal funds for a modernization and resiliency program with an estimated total value of $819.9 million.[^8] [^9] The program does not count converting a coal unit to natural gas as modernization, and bars the money for plants that plan a later switch to gas.[^10] That sets the federal terms against the stated rationale for the extension: in March 2025, the governor said converting AES to gas would take one to two years.[^11] And in June 2026, during dredging work on the Guayama bay channel, she described a waterway widened so AES could receive larger coal barges.[^12]

In August, the Senate ordered its Planning, Permits, Infrastructure and Urbanism Commission to investigate the plant's present and future operation.[^13]

## What this stands on

1. The Autoridad de Energía Eléctrica (AEE) and AES Puerto Rico signed a 'hoja de términos' to negotiate extending the cogeneradora's coal-burning operations until 2032. ([El Nuevo Día](https://www.elnuevodia.com/noticias/locales/notas/mas-cerca-acuerdo-para-extender-la-operacion-de-la-cogeneradora-aes-para-quemar-carbon-gasta-2032/), News)
2. The proposed extension would add five years of plant operation. ([elnuevodia.com](https://www.elnuevodia.com/noticias/locales/notas/mas-cerca-acuerdo-para-extender-la-operacion-de-la-cogeneradora-aes-en-quema-de-carbon-hasta-2032/), claim on record)
3. The AES Puerto Rico coal plant is located in Guayama. ([sutra.oslpr.org](https://sutra.oslpr.org/SutraFilesGen/161971/rs0585-26.pdf), claim on record)
4. The AES coal plant has approximately 510 megawatt generation capacity. ([sutra.oslpr.org](https://sutra.oslpr.org/SutraFilesGen/161971/rs0585-26.pdf), claim on record)
5. AES plant operations began in 2002. ([elnuevodia.com](https://www.elnuevodia.com/noticias/locales/notas/mas-cerca-acuerdo-para-extender-la-operacion-de-la-cogeneradora-aes-en-quema-de-carbon-hasta-2032/), claim on record)
6. AES Guayama plant contract with Puerto Rico electric authority expires 2027-11-29. ([periodicolaperla.com](https://www.periodicolaperla.com/actualidad/debia-cerrar-en-2027-pero-aes-pide-164-millones-para-extender-su-vida-util/), claim on record)
7. Puerto Rico Law Núm. 1-2025 extended AES coal generation authorization until December 2032. ([sutra.oslpr.org](https://sutra.oslpr.org/SutraFilesGen/161971/rs0585-26.pdf), claim on record)
8. AES Guayama coal plant was selected by US DOE on 2026-06-04 to negotiate $164.5 million federal funds. ([periodicolaperla.com](https://www.periodicolaperla.com/actualidad/debia-cerrar-en-2027-pero-aes-pide-164-millones-para-extender-su-vida-util/), claim on record)
9. The AES Puerto Rico plant modernization project has total estimated value of $819.9 million. ([periodicolaperla.com](https://www.periodicolaperla.com/actualidad/debia-cerrar-en-2027-pero-aes-pide-164-millones-para-extender-su-vida-util/), claim on record)
10. US DOE rules bar the awarded funds for coal plants planning future gas conversion. ([periodicolaperla.com](https://www.periodicolaperla.com/actualidad/debia-cerrar-en-2027-pero-aes-pide-164-millones-para-extender-su-vida-util/), claim on record)
11. In March 2025, the governor stated AES gas conversion would take 1 to 2 years. ([sutra.oslpr.org](https://sutra.oslpr.org/SutraFilesGen/161971/rs0585-26.pdf), claim on record)
12. In June 2026, the governor stated Guayama bay channel was widened for AES coal barges. ([sutra.oslpr.org](https://sutra.oslpr.org/SutraFilesGen/161971/rs0585-26.pdf), claim on record)
13. The resolution orders an investigation of AES Puerto Rico coal power plant. ([sutra.oslpr.org](https://sutra.oslpr.org/SutraFilesGen/161971/rs0585-26.pdf), claim on record)

## Provenance

Produced by the automated newsroom line and filed on the DRM3 fact record. Content hash sha256:97ae97a9210a9b922acedc10516b8f8f0925b44383ad0a6e97d057f9b121ee9f. Signed receipt RpgX4l1tJzUQ73VeYdIG... (Ed25519).
Machine-readable proof: https://news.pr/story/146d909e5c304747986b0e6dc8ebe7c5/proof
HTML edition: https://news.pr/story/146d909e5c304747986b0e6dc8ebe7c5

A signature proves who filed this and that it has not changed since. It never makes a claim true.